Deadlines for Project:
4 Feb (5pm) ................. Complete all traverse computations (primary, secondary, local)
11 Feb (end of class)..... Complete computation and checking of all found monuments, check that legal description closes
12 Feb (end of lab) ....... Complete comparison sketch, analysis of boundary evidence, work plan (sketch), final coordinate list
13 Feb (end of class)..... Review MTS requirements and begin survey plan
18 Feb (end of class) .... Complete survey plan according to MTS requirements
20 Feb (end of class) ..... Complete report and final organization of project package - submit project