SUR 3501 SPATIAL MEASUREMENTS SYSTEMS
Spring 2007
Schedule of Classes and Projects
These dates may change due to weather and other
unpredictable factors
|
DATE (week) |
Monday 4th Period |
Tuesday 8 10 Periods |
Wednesday 4th
Period |
Useful Info |
|
Jan 8-12 |
Jan 8:
Intro and Overview |
Project 1: Distance Measurement taping, pacing and total station |
Jan 10: Intro to Project 2 |
|
|
Jan 15-19 |
|
Project 2: EDM Calibration |
Jan 17: GPS |
|
|
Jan 22-26 |
Jan 22: Intro to Project 3 |
Project 3: GPS Point Positioning *Hand in Project Report A* |
Jan 24: Project 3 (computations) |
|
|
Jan 29 - Feb 2 |
Jan 29: Intro to Project 4 |
Project 4: OPUS Processing |
Jan 31: Intro to Project 5 |
|
|
Feb 5 - 9 |
Feb 5: Calculations/Fieldwork |
Project 5: Dual Frequency Static GPS |
Feb 7: DEMO of Leica post-processing software |
|
|
Feb 12 - 16 |
Feb 12: Analysis |
GPS Analysis |
Feb 14: Class will meet |
|
|
Feb 19 - 23 |
Feb 19: Intro to Project 6 |
Project 6: Map Accuracy Assessment |
Feb 21: Quiz 1 *Hand in Project Report B* |
·
AutoCad file
of GNV East Quad Sheet (UTM, NAD27) ·
About
Digital Raster Graphics (DRG) ·
About
Digital Line Graphs (DLG) |
|
Feb 26 - Mar 2 |
Feb 26: Review Quiz 1 |
Project 6: Intro to Project 7 |
Feb 28: LIDAR Lecture (Dr. Mohamed) |
**
QUIZ 1 KEY ** |
|
Mar 5 - 9 |
Mar 5: Riegl Lecture *Hand in Project Report C* |
Project 7(a): LIDAR demo |
Mar 7: Monitoring Survey |
|
|
Mar 12 - 16 |
Spring Break |
Spring Break |
Spring Break |
|
|
Mar 19 - 23 |
Mar 19: Intro to Project 7(b) |
Project 8: Monitoring Survey
(Lidar) |
Mar 21: Lidar Analysis |
Trig Levels Horizontal Calcs |
|
Mar 26 - 30 |
Mar 26: Survey of Wall
Control Points |
Project 7(d): Monitoring Survey( wall control) |
Mar 28: I want to meet individually with each
group in the class to discuss computations LAST DAY TO HAND IN COMPUTATIONS |
|
|
Apr 2 - 6 |
Apr 2; Review of methodology for
computing wall control coords |
Project 7(d), 7 (e): Monitoring Survey( wall control and GPS) |
Apr 4: Project 7 |
|
|
Apr 9 - 13 |
Apr 9: Review of computation issues |
Project 7 (e): Continue with Computations |
Apr 11: Continue with
computations no class meeting (I still have not received the Scanner data) |
|
|
April 16 - 20 |
Apr 16: Final Project
description |
Project 7 (f): Analysis of
Scanner data and wall distortions |
Apr 18: I will meet with individual groups |
|
|
Apr 23 - 27 |
Apr 23: Review |
Presentations (Groups) of Project
7 |
Apr 25: Quiz 2 *Hand in Project Report D* |